'Huge win for ratepayers': Flames agree to take on cost overruns, CMLC to be replaced as project manager
The City of Calgary released confidential material related to the new arena project Monday afternoon, but the mayor says council has already approved changes to the budget and the project manager.
In 2019, the city and Calgary Sports and Entertainment Corporation -- otherwise known as CSEC, the ownership group of the Flames -- agreed to split the cost of a $550 million arena 50/50.
Mayor Naheed Nenshi said they found that the budget would no longer work as they proceeded with detailed design work.
"It was built on an inverted bowl design which is very, very steep and it may not have worked in that particular piece of land and it would've been bad for accessibility. As we got into further design work, we realized there are some other things," the mayor told reporters Monday.
"For example, there weren't enough women's bathrooms and, in fact much to my surprise, the thought was that there may be too many luxury boxes and not enough seats for regular people."
The contract agreed to by council in 2019 included a clause that could see both sides split cost overruns up to $25 million.
Council has agreed to increase the city's share of the costs of the building by a maximum of $12.5 million, the mayor said. CSEC will also put up its share to match that city funding, but will also now be on the hook for any additional costs above the $25 million.
"Calgary Sports and Entertainment Corporation -- the Flames -- have agreed to take on all cost overruns and risk of constriction cost overruns. That is a huge win for ratepayers," said Nenshi.
In the just-released documents, the estimated cost for the arena is now $608.5 million. Of that, the city will pay $287.5 million (plus up to $10 million for prep work), while the Flames will pay $321 million.
CMLC OUT AS PROJECT MANAGER
The mayor also said the Calgary Municipal Land Corporation (CMLC) will no longer be the project manager of the new arena.
"CMLC will continue to be helpful, but if the Flames are taking on the risk of all the cost overruns, they want the ability to appoint a project manager of their choosing -- and I think that's a very legitimate request," Nenshi said.
A clearer picture of additional city costs is also coming to light, he added.
Site preparation and transportation costs for the area will also be the city's responsibility.
"There are the initial flood and site mediation costs that were already in there that we will be looking at capping at $10 million dollars. CMLC is also, as they would for any developer, doing some utility relocation and so on. That'll probably be about $4.5 million to $4.8 million," said Nenshi.
It's not clear what additional transportation costs will be, though the mayor said he believe them to be minor.
Council also ordered city administration to release confidential material about the deal to the public. That information is supposed to be available Monday afternoon, before council starts its debate on the changes.
CTVNews.ca Top Stories
Doctors ask Liberal government to reconsider capital gains tax change
The Canadian Medical Association is asking the federal government to reconsider its proposed changes to capital gains taxation, arguing it will affect doctors' retirement savings.
Keeping these exotic pets is 'cruel' and 'dangerous,' Canadian animal advocates say
Canadian pet owners are finding companionship beyond dogs and cats. Tigers, alligators, scorpions and tarantulas are among some of the exotic pets they are keeping in private homes, which pose risks to public safety and animal welfare, advocates say.
Prince William and wife Kate thank public for birthday messages for son Louis
Prince William and his wife Kate thanked the public for their messages which had been sent to mark the sixth birthday of their youngest son Louis on Tuesday.
She was the closest she'd ever been to meeting her biological father. Then life dealt her a blow
Anne Marie Cavner was the closest she'd ever been to meeting her biological father, but then life dealt her a blow. From an unexpected loss to a host of new relationships, a DNA test changed her life, and she doesn't regret a thing.
How quietly promised law changes in the 2024 federal budget could impact your day-to-day life
The 2024 federal budget released last week includes numerous big spending promises that have garnered headlines. But, tucked into the 416-page document are also series of smaller items, such as promising to amend the law regarding infant formula and to force banks to label government rebates, that you may have missed.
Which foods have the most plastics? You may be surprised
'How much plastic will you have for dinner, sir? And you, ma'am?' While that may seem like a line from a satirical skit on Saturday Night Live, research is showing it's much too close to reality.
'Catch-and-kill' strategy to be a focus as testimony resumes in Trump hush money case
A veteran tabloid publisher was expected to return to the witness stand Tuesday in Donald Trump's historic hush money trial.
Quebec farmers have been protesting since December. Is anyone listening?
Upset about high interest rates, growing paperwork and heavy regulatory burdens, protesting farmers have become a familiar sight across Quebec since December.
South Korean sentenced to 14 months in jail for killing 76 cats
South Korean man has been sentenced to 14 months in prison for killing 76 cats in one of the country's most gruesome cases of animal cruelty in recent years.