'Huge win for ratepayers': Flames agree to take on cost overruns, CMLC to be replaced as project manager
The City of Calgary released confidential material related to the new arena project Monday afternoon, but the mayor says council has already approved changes to the budget and the project manager.
In 2019, the city and Calgary Sports and Entertainment Corporation -- otherwise known as CSEC, the ownership group of the Flames -- agreed to split the cost of a $550 million arena 50/50.
Mayor Naheed Nenshi said they found that the budget would no longer work as they proceeded with detailed design work.
"It was built on an inverted bowl design which is very, very steep and it may not have worked in that particular piece of land and it would've been bad for accessibility. As we got into further design work, we realized there are some other things," the mayor told reporters Monday.
"For example, there weren't enough women's bathrooms and, in fact much to my surprise, the thought was that there may be too many luxury boxes and not enough seats for regular people."
The contract agreed to by council in 2019 included a clause that could see both sides split cost overruns up to $25 million.
Council has agreed to increase the city's share of the costs of the building by a maximum of $12.5 million, the mayor said. CSEC will also put up its share to match that city funding, but will also now be on the hook for any additional costs above the $25 million.
"Calgary Sports and Entertainment Corporation -- the Flames -- have agreed to take on all cost overruns and risk of constriction cost overruns. That is a huge win for ratepayers," said Nenshi.
In the just-released documents, the estimated cost for the arena is now $608.5 million. Of that, the city will pay $287.5 million (plus up to $10 million for prep work), while the Flames will pay $321 million.
CMLC OUT AS PROJECT MANAGER
The mayor also said the Calgary Municipal Land Corporation (CMLC) will no longer be the project manager of the new arena.
"CMLC will continue to be helpful, but if the Flames are taking on the risk of all the cost overruns, they want the ability to appoint a project manager of their choosing -- and I think that's a very legitimate request," Nenshi said.
A clearer picture of additional city costs is also coming to light, he added.
Site preparation and transportation costs for the area will also be the city's responsibility.
"There are the initial flood and site mediation costs that were already in there that we will be looking at capping at $10 million dollars. CMLC is also, as they would for any developer, doing some utility relocation and so on. That'll probably be about $4.5 million to $4.8 million," said Nenshi.
It's not clear what additional transportation costs will be, though the mayor said he believe them to be minor.
Council also ordered city administration to release confidential material about the deal to the public. That information is supposed to be available Monday afternoon, before council starts its debate on the changes.
CTVNews.ca Top Stories
Several flight attendants from Pakistan have gone missing after landing in Canada
Multiple flight attendants from Pakistan International Airlines have abandoned their jobs and are believed to have sought asylum in Canada in the past year and a half, a spokesperson for the government-owned airline says.
BREAKING Ottawa public school board, 3 Toronto-area school boards launch lawsuit against social media giants
The Ottawa-Carleton District School Board and three school boards in the Toronto-area have launched legal action against social media giants, accusing them of "disrupting students' fundamental right to education."
Rainfall warnings of up to 90 mm among weather alerts in effect for 7 provinces
Rainfall warnings of up to 90 millimetres, air quality advisories and other alerts have been issued for seven Canadian provinces, according to the latest forecasts.
Tipping is off the table at this Toronto restaurant
A Toronto restaurant introduced a surprising new rule that reduced the cost of a meal and raised the salaries of staff.
A Nigerian woman reviewed some tomato puree online. Now she faces jail
A Nigerian woman who wrote an online review of a can of tomato puree is facing imprisonment after its manufacturer accused her of making a “malicious allegation” that damaged its business.
Donald Trump assails judge and his daughter after gag order in N.Y. hush-money criminal case
Donald Trump lashed out Wednesday at the New York judge who put him under a gag order that bars him from commenting publicly about witnesses, prosecutors, court staff and jurors in his upcoming hush-money criminal trial.
A fight to protect the dignity of Michelangelo's David raises questions about freedom of expression
Michelangelo's David has been a towering figure in Italian culture since its completion in 1504. But in the current era of the quick buck, curators worry the marble statue's religious and political significance is being diminished.
Doctors visiting a Gaza hospital are stunned by the war's toll on Palestinian children
An international team of doctors visiting a hospital in central Gaza was prepared for the worst. But the gruesome impact Israel’s war against Hamas is having on Palestinian children still left them stunned.
China's latest EV is a 'connected' car from smart phone and electronics maker Xiaomi
Xiaomi, a well-known maker of smart consumer electronics in China, is joining the country's booming but crowded market for electric cars.