Minnesota court affirms approval of Enbridge's Line 3 oil pipeline
The Minnesota Court of Appeals on Monday affirmed state regulators' key approvals of Enbridge Energy's Line 3 oil pipeline replacement project, in a dispute that drew over 1,000 protesters to northern Minnesota last week.
A three-judge panel ruled 2-1 that the state's independent Public Utilities Commission correctly granted Enbridge the certificate of need and route permit that the Canadian-based company needed to begin construction on the 337-mile (542-kilometre) Minnesota segment of a larger project to replace a 1960s-era crude oil pipeline that has been deteriorating and can run at only half capacity.
Pipeline opponents can appeal the decision to the Minnesota Supreme Court. They planned to comment in detail later Monday but immediately urged President Joe Biden to intervene.
Tribal and climate change groups, plus the state Department of Commerce, had asked the appeals court to reject the approvals. They argued, among other things, that Enbridge's oil demand projections failed to meet the legal requirements. Enbridge and the PUC said the projections complied with the rules.
"With an existing, deteriorating pipeline carrying crude oil through Minnesota, there was no option without environmental consequences," wrote Judge Lucinda Jesson, joined by Judge Michael Kirk. "The challenge: to balance those harms. There was no option without impacts on the rights of Indigenous peoples. The challenge: to alleviate those harms to the extent possible. And there was no crystal ball to forecast demand for crude oil in this ever-changing environment."
But Judge Peter Reyes dissented, agreeing with opponents that the oil demand forecast was flawed. He said the project benefits Canadian oil producers but would have negative consequences for the hunting, fishing, and other rights of the Red Lake and White Earth tribes and provide no benefit to the state.
"Such a decision cannot stand. Enbridge needs Minnesota for its new pipeline," Reyes wrote. "But Enbridge has not shown that Minnesota needs the pipeline."
Enbridge said in a statement that the decision is confirmation that the commission thoroughly reviewed the project and gave the appropriate approvals.
"Line 3 has passed every test through six years of regulatory and permitting review including 70 public comment meetings, appellate review and reaffirmation of a 13,500-page (environmental impact statement), four separate reviews by administrative law judges, 320 route modifications in response to stakeholder input, and multiple reviews and approvals by the Minnesota Public Utilities Commission for the project's certificate of need and route permit."
At least 1,000 activists from across the country gathered at construction sites near the headwaters of the Mississippi River early last week. They called on Biden to cancel the project, as he did with the Keystone XL pipeline on his first day in office. Nearly 250 people were arrested, in addition to more than 250 arrests since construction began in December. A smaller group marched Thursday to the Minneapolis office of Democratic Sen. Amy Klobuchar.
The Line 3 replacement would carry Canadian tar sands oil and regular crude from Alberta to Enbridge's terminal in Superior, Wisconsin. The project is nearly done except for the Minnesota leg, which is about 60% complete.
Opponents of the more than $7 billion project say the heavy oil would accelerate climate change and risk spills in sensitive areas where Native Americans harvest wild rice, hunt, fish, gather medicinal plants and claim treaty rights.
Calgary-based Enbridge says the replacement Line 3 will be made of stronger steel and will better protect the environment while restoring its capacity to carry oil and ensure reliable deliveries to U.S. refineries. It underwent a rigorous environmental permitting process. The old line currently runs at about half its capacity because it's increasingly subject to corrosion and cracking.
Activists are vowing to keep up a summer of resistance against the project amid the escalating battle over energy projects and rising awareness that racial minorities suffer disproportionate harm from environmental damage. And they're drawing parallels with the fight over the Dakota Access pipeline, which was the subject of major protests near the Standing Rock Reservation in the Dakotas in 2016 and 2017.
"Minnesota does not need this conflict. Minnesota has already had enough police problems, and we are very upset at the level of private security and police forces that are all over the north right now," Winona LaDuke, executive director of the Indigenous-based environmental group Honor the Earth, told reporters on a conference call Friday. "For a Canadian corporation. So we'll stand our ground ... and more will be coming. Guaranteed."
"If the Biden administration is under any illusions, this is now very much a national fight that people are going to be knowing more and more about," said Bill McKibben, founder of the climate change group 350.org. "People are already flooding in from all parts of the country."
CTVNews.ca Top Stories
Poilievre will do 'anything to win,' must condemn Alex Jones endorsement: Trudeau
Prime Minister Justin Trudeau is ramping up his attacks on Conservative Leader Pierre Poilievre as he promotes his government's federal budget.
'My stomach dropped': Winnipeg man speaks out after being criminally harassed following single online date
A Winnipeg man said a single date gone wrong led to years of criminal harassment, false arrests, stress and depression.
New evidence challenges the Pentagon's account of a horrific attack as the U.S. withdrew from Afghanistan: CNN exclusive
New video evidence uncovered by CNN significantly undermines two Pentagon investigations into an ISIS-K suicide attack outside Kabul airport, during the American withdrawal from Afghanistan in 2021.
'One of the single most terrifying things ever': Ontario couple among passengers on sinking tour boat in Dominican Republic
A Toronto couple are speaking out about their 'extremely dangerous' experience on board a sinking tour boat in the Dominican Republic last week.
All Alberta wildfires to date in 2024 believed to be human-caused: province
There are 63 wildfires burning in Alberta's forest protection area as of Wednesday morning and seven mutual aid fires, including one in the Municipal District of Peace.
Video shows suspects waving weapons, smashing glass in Toronto jewelry store robbery
Arrests have been made after five men were captured on video rampaging through a jewelry store in Toronto, waving weapons and smashing glass display cases.
Pilot proposes to flight attendant girlfriend in front of passengers
A Polish pilot proposed to his flight attendant girlfriend during a flight from Warsaw to Krakow, and she said yes.
Ottawa injects another $36M into fund for those seriously injured or killed by vaccines
The federal government has added $36.4 million to a program designed to support people who have been seriously injured or killed by vaccines since the end of 2020.
Ex-SNC executive sentenced to prison term in bridge bribery case
The RCMP says a former SNC-Lavalin executive has been sentenced to three and a half years in prison in connection with a bribery scheme for a bridge repair contract in Montreal.