Regulator rules in favour of Trans Mountain route deviation

The Canada Energy Regulator has approved Trans Mountain Corp.'s application to modify the pipeline's route, a decision that could spare the government-owned pipeline project from an additional nine-month delay.
The regulator made the ruling Tuesday, just one week after hearing oral arguments from Trans Mountain and a B.C. First Nation that opposes the route change.
It didn't release the reasons for its decision Tuesday, saying those will be publicized in the coming weeks.
By siding with Trans Mountain Corp., the regulator is allowing the pipeline company to alter the route slightly for a 1.3-kilometre stretch of pipe in the Jacko Lake area near Kamloops, B.C., as well as the construction method for that section.
Trans Mountain Corp. had said it ran into engineering difficulties in the area related to the construction of a tunnel, and warned that sticking to the original route could result in up to a nine-month delay in the pipeline's completion, as well as an additional $86 million more in project costs.
Trans Mountain has been hoping to have the pipeline completed by early 2024.
But Trans Mountain's application was opposed by the Stk’emlúpsemc te Secwépemc Nation, whose traditional territory the pipeline crosses and who had only agreed to the originally proposed route.
In their regulatory filing, the First Nation stated the area has "profound spiritual and cultural significance'' to their people, and that they only consented to the pipeline's construction with the understanding that Trans Mountain would minimize surface disturbances by implementing specific trenchless construction methods.
The Stk’emlúpsemc te Secwépemc argued that Trans Mountain never said its originally proposed construction method was impossible, only that it couldn't be done in time to meet a Jan. 1 in-service date for the pipeline.
The First Nation didn't respond to a request for comment by publication time.
The Trans Mountain pipeline is Canada's only pipeline system transporting oil from Alberta to the West Coast. Its expansion, which is currently underway, will boost the pipeline's capacity to 890,000 barrels per day (bpd) from 300,000 bpd currently.
The pipeline — which was bought by the federal government for $4.5 billion in 2018 after previous owner Kinder Morgan Canada Inc. threatened to scrap the pipeline's planned expansion project in the face of environmentalist opposition and regulatory hurdles — has already been plagued by construction-related challenges and delays.
Its projected price tag has since spiralled: first to $12.6 billion, then to $21.4 billion and most recently to $30.9 billion (the most recent capital cost estimate, as of March of this year).
Keith Stewart with Greenpeace Canada said it's alarming to see the regulator over-rule the wishes of Indigenous people in order to complete a pipeline on deadline.
"Every Canadian should be outraged that our public regulator is allowing a publicly owned pipeline to break a promise to Indigenous people to protect lands of spiritual and cultural significance," Stewart said.
The federal government has already approved a total of $13 billion in loan guarantees to help Trans Mountain secure the financing to cover the cost overruns.
Trans Mountain Corp. has blamed its budget problems on a variety of factors, including inflation, COVID-19, labour and supply chain challenges, flooding in B.C. and unexpected major archeological discoveries along the route.
Given the Canadian regulatory system has a reputation for being slow and cumbersome, it was surprising to see the Canada Energy Regulator rule so quickly on Trans Mountain's route deviation request, said Richard Masson, executive fellow with the University of Calgary's School of Public Policy.
"It's a challenging decision to have to make, when you've got a $30 billion pipeline that needs to be completed," Masson said.
"If there's no feasible way to do that tunnel, then I guess you have to allow for this."
Masson added that if the regulator had denied Trans Mountain's request, it would have been bad news for taxpayers as well as the federal government, which is seeking to divest the pipeline and has already entered into negotiations with several interested Indigenous-led buyers.
It also would have been bad news for Canadian oil companies, who have been eagerly anticipating the pipeline's start date to begin shipping barrels to customers.
"If this can result in the pipeline being completed by year-end and started up in the first quarter, that's good news. The world is still looking for oil, and oil prices are up at US$90 a barrel," Masson said.
--
This report by The Canadian Press was first published on Sept. 25, 2023.
CTVNews.ca Top Stories

Poilievre calling on 'unelected' Senate to 'immediately' pass farm fuels carbon tax bill
Conservative Leader Pierre Poilievre is pushing for MPs to call on senators to 'immediately' pass a bill that would exempt certain farm fuels from the carbon price.
Chicago Blackhawks to terminate Corey Perry's contract after finding 'unacceptable' conduct
The Chicago Blackhawks said Corey Perry engaged in unacceptable conduct and took a step Tuesday toward terminating his contract, the latest twist involving the veteran winger who was mysteriously scratched and sent home last week without explanation.
Short-term rental tax changes left out of Freeland's bill to implement fiscal update measures, here's why
Finance Minister Chrystia Freeland will be tabling an omnibus bill to pass measures she promised in last week's fall economic statement. Missing from the package are the government's promised plans to crack down on short-term rentals, while the Liberal promise to double the carbon tax rural rebate top-up, is included.
Frank the Tank, a tortoise found wandering a B.C. field, gets a new home
Adoption requests came from as far away as New Zealand, but Frank the Tank, a 17-kilogram tortoise found wandering in a Richmond bok choy field last month, will be staying in British Columbia.
French police arrest yoga guru accused of exploiting female followers
French authorities arrested the leader of a multinational tantric yoga organization Tuesday on suspicion of indoctrinating female followers for sexual exploitation.
OPINION Advice on dealing with 'quiet hiring' in the workplace
In a column for CTVNews.ca, personal finance writer Christopher Liew tackles 'quiet hiring' -- a term referring to companies that quietly hire from their own talent pool rather than look elsewhere -- and outlines some tips for employees on how to take advantage of the practice.
Customer sues Chopt eatery chain over salad that she says contained a piece of manager's finger
A customer has filed a lawsuit against the fast casual chain Chopt over a salad that she says contained a piece of the manager's finger.
Alex Murdaugh sentenced to 27 years for financial fraud after victims angrily confront him in court By Jeffrey Collins
For years, South Carolina attorney Alex Murdaugh looked his anguished clients in the eyes and promised to help them with their medical bills, their suffering or simply to survive. Then he stole most, if not all, of what he won for many of them.
High-fat flight is first jetliner to make fossil-fuel-free transatlantic crossing from London to NY
The first commercial airliner to cross the Atlantic on a purely high-fat, low-emissions fuel flew Tuesday from London to New York in a step toward achieving what supporters called 'jet zero.'