Regulator denies Trans Mountain's pipeline variance request
The Canada Energy Regulator has denied a request by Trans Mountain Corp. for a variance on a section of pipeline in B.C., a development that the company has said could delay construction of the ongoing expansion project and push back the pipeline's start date.
The regulator issued its ruling Tuesday, but — for the purpose of expediency — did not provide its reasons for the decision. It said it will provide its written reasons at a later date.
Trans Mountain Corp., the crown corporation that is building the pipeline expansion, had applied for the variance after running into what it said were construction challenges related to hard rock between Chilliwack and Hope, B.C.
The company had requested permission to use a different diameter, wall thickness and coating for a 2,300-metre section of pipeline than it had originally been approved for.
At a recent oral hearing in Calgary, Trans Mountain Corp. said that being denied the variance could add an additional 55 to 60 days to the project's construction schedule.
This could mean, argued chief project execution officer Corey Goulet at the hearing, that Trans Mountain may not be able to complete the project in time for an anticipated first-quarter 2024 start date.
"We'd be at least, you know, a month after our plan, maybe more," Goulet said, according to the official transcript of the hearing.
The development is only the latest in a string of construction-related hurdles that have plagued the Trans Mountain expansion project.
The pipeline is Canada's only oil pipeline to the west coast. Its expansion will boost the pipeline's capacity to 890,000 barrels per day from 300,000 bpd currently and improve access to export markets for Canadian oil companies.
But the project's costs have spiralled through the course of construction from an original estimate of $5.4 billion to the most recent estimate of $30.9 billion.
Earlier this fall, Trans Mountain Corp. also applied to the regulator for permission to alter the route for a 1.3-km stretch of pipe in the Jacko Lake area near Kamloops, B.C., due to difficulties drilling a tunnel.
The regulator granted that request, even though a B.C. First Nation opposed the route alteration.
Trans Mountain has been racing against the clock to complete the project on schedule in order to prevent additional cost overruns as well as the approximately $200 million per month in lost revenue it would incur if the pipeline doesn't begin shipping oil as early as expected.
Last week, a group of oil shippers including Canadian Natural Resources Ltd., Marathon Petroleum, Parkland Refining, PetroChina Canada Ltd. and Suncor Energy Inc. wrote a letter to the Canada Energy Regulator emphasizing the importance of a timely completion of the pipeline expansion project.
"However, should the variance lead to any adverse effects or unforeseen impacts affecting the shippers, it is imperative that Trans Mountain bears all responsibility for rectifying these issues in a timely and reasonable manner and at its sole cost, risk and expense," the shippers' letter stated.
Trans Mountain testified at the hearing that using a different diameter and thickness of pipe for a 2,300-metre section of the project would not reduce the overall volumes of oil that could be transported by the expanded pipeline.
--
This report by The Canadian Press was first published on Dec. 5, 2023.
CTVNews.ca Top Stories
Canadian team told Trump's tariffs unavoidable right now, but solutions on the table in surprise Mar-a-Lago meeting
During a surprise dinner at Mar-a-Lago, representatives of the federal government were told U.S. tariffs from the incoming Donald Trump administration cannot be avoided in the immediate term, two government sources tell CTV News.
Pedestrian killed by Via Rail train near Kingston, Ont.
Regular rail traffic has resumed with severe delays.
Muskoka reacts to major snowfall, hundreds stuck on Highway 11
From road closures, power outages, weather declarations and nonstop shovelling, Muskoka residents were faced with nearly a metre of persistent snowfall on Saturday.
Saskatoon priest accused of sexual assault says he meant to encourage young girl with hug and kiss
A Saskatoon priest accused of sexual assault says he meant to encourage and reassure a young girl when he hugged and kissed during his testimony at Saskatoon Provincial Court Friday.
Beef prices reach record highs in Canada
The cost of beef continues to rise, reaching record highs on grocery store shelves ahead of the busiest time for many grocers and butchers before the holiday season.
Trump threatens 100% tariff on the BRIC bloc of nations if they act to undermine U.S. dollar
U.S. president-elect Donald Trump on Saturday threatened 100 per cent tariffs against a bloc of nine nations if they act to undermine the U.S. dollar.
Bob Bryar, drummer for rock band My Chemical Romance, dead at 44
Bob Bryar, former drummer for the band My Chemical Romance, has died. He was reportedly 44.
Toronto man accused of posing as surgeon, giving four women injections
A 29-year-old Toronto man has been charged after allegedly posing as a surgeon and providing cosmetic procedures on several women.
'Disappointing': Toronto speed camera cut down less than 24 hours after being reinstalled
A Toronto speed camera notorious for issuing tens of thousands of tickets to drivers has been cut down again less than 24 hours after it was reinstalled.