Ninth Avenue Bridge to Inglewood officially opens after delay, cost overrun
A bridge connecting the East Village and Inglewood is now fully open for vehicle and pedestrian traffic.
The Ninth Avenue S.E. bridge replaced the 110-year-old crossing into Inglewood. The project was more than $2 million over budget and delayed by more than a year-and-a-half.
"Bridge projects of this type and scale have very unique challenges and opportunities, which makes achieving this milestone all the more rewarding for the entire team," said project manager Evan Fer.
Initially set to cost $23 million and be completed by the end of 2020, issues with the steel supply pushed the timeline back and increased the budget. The final cost for the bridge comes in at $25.1 million, with $5.24 million coming from the province and $7 million coming from the Calgary Municipal Land Corporation.
The new bridge improves flood resiliency and enhances the walking and cycling connections between the two areas.
The structure opened to limited vehicle traffic in February of this year, but pathway work for pedestrians continued into June.
A temporary bridge over the Elbow River allowed traffic to flow through construction. The temporary crossing was removed in April.
CTVNews.ca Top Stories
'State or state-sponsored actor' believed to be behind B.C. government hacks
The head of British Columbia’s civil service has revealed that a “state or state-sponsored actor” is behind multiple cyber-security incidents against provincial government networks.
Here's how much more Canadian landlords are asking for now, according to a just-released report
A new report says the average asking rent for a home in Canada in April was up 9.3 per cent compared with a year ago, while a slight month-over-month increase was also recorded for the first time since January.
Rare severe solar storm Friday could bring spectacular aurora light show across Canada
A rare and severe solar storm is expected to bring spectacular displays of the northern lights, also known as aurora borealis, across much of Canada and parts of the United States on Friday night.
What is basic income, and how would it impact me?
Parliamentarians are considering a pair of bills aiming to lift people out of poverty through a basic income program, but some fear these types of systems could result in more taxes for Canadians who are already financially struggling.
Canada abstains from Palestinian UN membership vote but supports two-state solution
Canada was one of 25 countries that abstained from a United Nations vote on Palestinian membership that passed with overwhelming support on Friday.
More than half the Canadians once detained in Syrian camps for suspected ISIS family members have returned home
A total of 29 Canadians have been freed from detention camps in northeast Syria and brought back to Canada since human rights advocates began lobbying for their release years ago.
'I may have some nightmares:' Man survives being bitten by 2 sharks in Bahamas
A man who was bitten by two sharks in the Bahamas said Thursday he's 'thankful that I'm here' while sharing his story of survival.
Out-of-control wildfire burning near Fort McMurray
As of 9 a.m. on Friday, the wildfire burning 28 kilometres southwest of the northeastern Alberta city was 25 hectares in size.
Mexico's president accuses press and volunteer searchers for missing people of 'necrophilia'
The administration of Mexico's president has accused the press and volunteer searchers who look for the bodies of missing people of 'necrophilia,' comments that drew criticism this week.