'Huge win for ratepayers': Flames agree to take on cost overruns, CMLC to be replaced as project manager
The City of Calgary released confidential material related to the new arena project Monday afternoon, but the mayor says council has already approved changes to the budget and the project manager.
In 2019, the city and Calgary Sports and Entertainment Corporation -- otherwise known as CSEC, the ownership group of the Flames -- agreed to split the cost of a $550 million arena 50/50.
Mayor Naheed Nenshi said they found that the budget would no longer work as they proceeded with detailed design work.
"It was built on an inverted bowl design which is very, very steep and it may not have worked in that particular piece of land and it would've been bad for accessibility. As we got into further design work, we realized there are some other things," the mayor told reporters Monday.
"For example, there weren't enough women's bathrooms and, in fact much to my surprise, the thought was that there may be too many luxury boxes and not enough seats for regular people."
The contract agreed to by council in 2019 included a clause that could see both sides split cost overruns up to $25 million.
Council has agreed to increase the city's share of the costs of the building by a maximum of $12.5 million, the mayor said. CSEC will also put up its share to match that city funding, but will also now be on the hook for any additional costs above the $25 million.
"Calgary Sports and Entertainment Corporation -- the Flames -- have agreed to take on all cost overruns and risk of constriction cost overruns. That is a huge win for ratepayers," said Nenshi.
In the just-released documents, the estimated cost for the arena is now $608.5 million. Of that, the city will pay $287.5 million (plus up to $10 million for prep work), while the Flames will pay $321 million.
CMLC OUT AS PROJECT MANAGER
The mayor also said the Calgary Municipal Land Corporation (CMLC) will no longer be the project manager of the new arena.
"CMLC will continue to be helpful, but if the Flames are taking on the risk of all the cost overruns, they want the ability to appoint a project manager of their choosing -- and I think that's a very legitimate request," Nenshi said.
A clearer picture of additional city costs is also coming to light, he added.
Site preparation and transportation costs for the area will also be the city's responsibility.
"There are the initial flood and site mediation costs that were already in there that we will be looking at capping at $10 million dollars. CMLC is also, as they would for any developer, doing some utility relocation and so on. That'll probably be about $4.5 million to $4.8 million," said Nenshi.
It's not clear what additional transportation costs will be, though the mayor said he believe them to be minor.
Council also ordered city administration to release confidential material about the deal to the public. That information is supposed to be available Monday afternoon, before council starts its debate on the changes.
CTVNews.ca Top Stories
Former homicide detective explains how police will investigate shooting outside Drake's Bridle Path mansion
Footage from dozens of security cameras in the area of Drake’s Bridle Path mansion could be the key to identifying the suspect responsible for shooting and seriously injuring a security guard outside the rapper’s sprawling home early Tuesday morning, a former Toronto homicide detective says.
Federal government grants B.C.'s request to recriminalize hard drugs in public spaces
The federal government is granting British Columbia's request to recriminalize hard drugs in public spaces, nearly two weeks after the province asked to end its pilot project early over concerns of public drug use.
Stormy Daniels describes meeting Trump during occasionally graphic testimony in hush money trial
Stormy Daniels took the witness stand Tuesday at Donald Trump's hush money trial, describing for jurors a sexual encounter the porn actor says she had with him in 2006 that resulted in her being paid off to keep silent during the presidential race 10 years later.
MPs agree Canadian gov't should improve new disability benefit
The federal government needs to safeguard the incoming Canada Disability Benefit from clawbacks and do more to ensure it actually meets the stated aim of lifting people living with disabilities out of poverty, MPs from all parties agree.
Bye-bye bag fee: Calgary repeals single-use bylaw
A Calgary bylaw requiring businesses to charge a minimum bag fee and only provide single-use items when requested has officially been tossed.
CFL suspends Argos QB Chad Kelly at least nine games following investigation
The CFL suspended Toronto Argonauts quarterback Chad Kelly for at least nine regular-season games Tuesday following its investigation into a lawsuit filed by a former strength-and-conditioning coach against both the player and club.
Boy Scouts of America changing name for first time in 114 years, aiming for inclusivity
The Boy Scouts of America is changing its name for the first time in its 114-year history and will become Scouting America. It's a significant shift as the organization emerges from bankruptcy following a flood of sexual abuse claims and seeks to focus on inclusion.
opinion Tom Mulcair: Trudeau's handling of Poilievre's 'wacko' House turfing a clear sign of Liberal desperation
When Speaker Greg Fergus tossed out Pierre Poilievre from the House last week, "those of us who have experience as parliamentarians simply couldn't believe our eyes," writes former NDP leader Tom Mulcair in his column for CTVNews.ca
New charges for Ont. woman who previously admitted to defrauding doulas
The Brantford, Ont. woman who was previously sentenced to house arrest after admitting to deceiving doulas has been charged again in connection to a new victim.