'Huge win for ratepayers': Flames agree to take on cost overruns, CMLC to be replaced as project manager
The City of Calgary released confidential material related to the new arena project Monday afternoon, but the mayor says council has already approved changes to the budget and the project manager.
In 2019, the city and Calgary Sports and Entertainment Corporation -- otherwise known as CSEC, the ownership group of the Flames -- agreed to split the cost of a $550 million arena 50/50.
Mayor Naheed Nenshi said they found that the budget would no longer work as they proceeded with detailed design work.
"It was built on an inverted bowl design which is very, very steep and it may not have worked in that particular piece of land and it would've been bad for accessibility. As we got into further design work, we realized there are some other things," the mayor told reporters Monday.
"For example, there weren't enough women's bathrooms and, in fact much to my surprise, the thought was that there may be too many luxury boxes and not enough seats for regular people."
The contract agreed to by council in 2019 included a clause that could see both sides split cost overruns up to $25 million.
Council has agreed to increase the city's share of the costs of the building by a maximum of $12.5 million, the mayor said. CSEC will also put up its share to match that city funding, but will also now be on the hook for any additional costs above the $25 million.
"Calgary Sports and Entertainment Corporation -- the Flames -- have agreed to take on all cost overruns and risk of constriction cost overruns. That is a huge win for ratepayers," said Nenshi.
In the just-released documents, the estimated cost for the arena is now $608.5 million. Of that, the city will pay $287.5 million (plus up to $10 million for prep work), while the Flames will pay $321 million.
CMLC OUT AS PROJECT MANAGER
The mayor also said the Calgary Municipal Land Corporation (CMLC) will no longer be the project manager of the new arena.
"CMLC will continue to be helpful, but if the Flames are taking on the risk of all the cost overruns, they want the ability to appoint a project manager of their choosing -- and I think that's a very legitimate request," Nenshi said.
A clearer picture of additional city costs is also coming to light, he added.
Site preparation and transportation costs for the area will also be the city's responsibility.
"There are the initial flood and site mediation costs that were already in there that we will be looking at capping at $10 million dollars. CMLC is also, as they would for any developer, doing some utility relocation and so on. That'll probably be about $4.5 million to $4.8 million," said Nenshi.
It's not clear what additional transportation costs will be, though the mayor said he believe them to be minor.
Council also ordered city administration to release confidential material about the deal to the public. That information is supposed to be available Monday afternoon, before council starts its debate on the changes.
CTVNews.ca Top Stories
MPP Sarah Jama asked to leave Ontario legislature for wearing keffiyeh
MPP Sarah Jama was asked to leave the Legislative Assembly of Ontario by House Speaker Ted Arnott on Thursday for wearing a keffiyeh, a garment which has been banned at Queen’s Park.
Mountain guide dies after falling into a crevasse in Banff National Park
A man who fell into a crevasse while leading a backcountry ski group deep in the Canadian Rockies has died.
2 teens charged in Halifax homicide: police
Two teenagers have been charged with second-degree murder in connection to an alleged homicide near the Halifax Shopping Centre earlier this week.
'Deep ignorance': Calls for Manitoba trustee to resign sparked after comments about Indigenous people and reconciliation
A rural Manitoba school trustee is facing calls to resign over comments he made about Indigenous people and residential schools earlier this week.
ByteDance prefers TikTok shutdown in U.S. if legal options fail, Reuters sources say
TikTok owner ByteDance would prefer to shut down its loss-making app rather than sell it if the Chinese company exhausts all legal options to fight legislation to ban the platform from app stores in the U.S., four sources said.
12-year-old hippo in Japan raised as a male discovered to be a female
When Gen-chan arrived at a zoo in Japan in 2017, no one questioned whether the then-five-year-old hippopotamus was a boy. Seven years later, zoo staff made a surprising discovery: Gen-chan, now 12, was female.
Here's why Harvey Weinstein's New York rape conviction was tossed and what happens next
Here's what you need to know about why movie mogul Harvey Weinstein's rape conviction was thrown out and what happens next.
Improve balance and build core strength with this exercise
When it comes to cardiovascular fitness, you may tend to focus on activities that move you forward, such as walking, running and cycling.
Legendary hockey broadcaster Bob Cole dies at 90: CBC
Bob Cole, a welcome voice for Canadian hockey fans for a half-century, has died at the age of 90. Cole died Wednesday night in St. John's, N.L., surrounded by his family, his daughter, Megan Cole, told the CBC.