Province gives the go ahead on a new Green Line plan assuring cost certainty
The Green Line board says the City of Calgary has an agreement with the province in regards to a new phased procurement strategy on the massive project.
The first phase will consist of building the LRT from Shepard in the southeast to Eau Claire at the same time, while using the existing red and blue lines.
Previously it was broken down into three phases.
“The business case for Green Line remains strong," says Don Fairbairn, executive chair of the Green Line Board.
"Moving forward with a new procurement will bring greater cost certainty and ensure we can deliver on our mandate to build Green Line, within council-approved direction, on behalf of our funding partners and for Calgarians."
The previous plan would have seen construction start this summer between Shepard and Inglewood.
The board is now seeking bids, something Fairbairn believes will not be an issue.
This also means phase 2 from Eau Claire, across the Bow River to 16 Avenue North, will advance if cost of escalation and other risks do not materialize in phase 1.
The board says a 0.5 per cent increase in escalation costs results in an additional $100 million for the project
This plan was sent for provincial approval on May 28th.
The board says the federal funding business case that is with the province now needs to get the stamp of approval before it is then sent to Ottawa, something Fairbairn does not have a timeline for.
However, Fairbairn is very confident the province will support the plan.
“We have an agreement with the province that this procurement is acceptable to them, and most importantly, it's acceptable to us," he said.
As for when construction could start, no timeline has been given.
The city has said before that it was delayed until at least 2022.
Mayor Naheed Nenshi calls Wednesday an exciting day and is still targeting 2025-2026 for completion.
“It is certainly that we are a bit delayed," he said. “I am hopeful that we will still be able to get close to there, it may drop a little bit. But as the results of this procurement come in we’ll be able to add the timeline.”
The province did allocate $25 million in Budget 2021 for the Green Line and set aside another $341 million in the subsequent two budgets. The federal government has also committed more than $1.5 billion to the project.
The Green Line will cost an estimated $5.5 billion.
CTVNews.ca Top Stories
New Norad commander calls Canada's defence policy update 'very encouraging'
American troops will be spending more time training in the Far North, the new commander of Norad says, a strategy that fits 'hand-in-glove' with Canada's renewed focus on Arctic defence.
opinion The special relationship between King Charles and the Princess of Wales
Royal commentator Afua Hagan writes that when King Charles recently admitted Catherine to the Order of the Companions of Honour, it not only made history, but it reinforced the strong bond between the King and his beloved daughter-in-law.
'I was scared': Ontario man's car repossessed after missing two repair loan payments
An Ontario man who took out a loan to pay for auto repairs said his car was repossessed after he missed two payments.
$70M Lotto Max winners kept prize a secret from family for 2 months
During a special winner celebration near their hometown, Doug and Enid shared the story of how they discovered they were holding a Lotto Max ticket worth $70 million and how they kept this huge secret for so long.
Are Canadians getting sick from expired food?
A new survey by Dalhousie University's Agri-Food Analytics Lab asked Canadians about their food consumption habits amid rising prices.
Documents reveal Ottawa's efforts to get Loblaw, Walmart on board with grocery code
It was evident to the federal government as early as last fall that Loblaw and Walmart might be holdouts to the grocery code of conduct, jeopardizing the project's success.
Charlie Woods, son of Tiger, shoots 81 in U.S. Open qualifier
Charlie Woods failed to advance in a U.S. Open local qualifying event Thursday, shooting a 9-over 81 at Legacy Golf & Tennis Club.
Improve balance and build core strength with this exercise
When it comes to cardiovascular fitness, you may tend to focus on activities that move you forward, such as walking, running and cycling.
B.C. tenants evicted for landlord's use after refusing large rent increase to take over neighbouring suite
Ashley Dickey and her mother rented part of the same Coquitlam duplex in three different decades under three different landlords.