After more than four years of construction and at least $34 billion in costs, the Trans Mountain pipeline expansion project is nearly complete. Here's a look at what milestones to expect in the coming weeks as the massive pipeline gets ready to start shipping Canadian oil to the West Coast:
Resolution of B.C. construction challenges: Crown corporation Trans Mountain Corp. has been dealing with construction-related challenges in the Fraser Valley between Hope and Chilliwack, where it encountered an “obstruction” when trying to pull the pipe into the horizontal hole that had been drilled for it. The setback forced the company to remove the pipe temporarily to address the issue, but Trans Mountain Corp. says it is nearing a resolution and expects to be able to re-install the pipe in that section within the next couple of weeks.
Mechanical completion: This marks the final stage of physical construction of the pipeline. Once the challenging segment of pipe has been successfully pulled back into its location, Trans Mountain will be able to complete the “final weld,” or what is formally known as mechanical completion.
Leave To Open: After construction is finished but before the pipeline can be put into service, there are several regulatory steps that must be completed. In accordance with the Canada Energy Regulator Act, companies require permission from the CER before commencing operations of a pipeline. This process is called Leave to Open and requires results from a series of inspections and safety tests. Because the Trans Mountain project has been constructed in phases, the company has been applying for Leave to Open permission in stages in order to allow flexibility during the commissioning and startup process.
Line fill: This term is used to describe the final stages of work required to prepare and ultimately fill the expanded pipeline system with more than four million barrels of oil. The process will take several weeks to complete. While line fill has not yet started on the newly constructed pipe, part of the Trans Mountain expansion project involves reactivating two older pipeline segments that had been maintained in a deactivated state. Initial line fill has already begun in B.C. on that section of the project.
In-service: This term refers to when the entire expanded pipeline system is fully operational and ready to make regular deliveries. According to a Bloomberg report, China's Sinochem Group has purchased one of the first shipments, a 550,000-barrel cargo from Suncor Energy Inc., which will load from the Trans Mountain expansion pipeline in May-June. Trans Mountain is continuing to target an in-service date sometime in the second quarter of 2024.
Cleanup and reclamation: Once the expanded pipeline is operational, required cleanup and reclamation work will continue in the project's construction zone.
This report by The Canadian Press was first published March 26, 2024.
CTVNews.ca Top Stories
Feds 'not interested' in investing in LNG facilities: energy minister
Energy and Natural Resources Minister Jonathan Wilkinson says the federal government is 'not interested' in subsidizing future liquefied natural gas (LNG) projects, including the electrification of projects currently in the works.
Chants of 'shame on you' greet guests arriving for the annual White House correspondents' dinner
An election-year roast of U.S. President Joe Biden before journalists, celebrities and politicians at the annual White House correspondents' dinner Saturday.
Global measles cases nearly doubled in one year, researchers say
The number of measles cases around the world nearly doubled from 2022 to 2023, researchers say, presenting a challenge to efforts to achieve and maintain elimination status in many countries.
Fair share: the right office solution can take finding the right partner
The rise of remote and hybrid work has made it harder to justify a full office, so more are leaning on co-working spaces that they share with many others for convenience and cost savings. The choice, however, comes at the expense of privacy and control.
What Trudeau's podcast appearances say about the Liberals' next ballot box question
Trudeau recently appeared on four podcasts as he travels the country talking up the Liberals' latest budget, which he's pitching as a plan to inject more economic fairness into society for those under 40 — a cohort that has kept Trudeau in power since 2015 but is increasingly turning to Conservative Leader Pierre Poilievre.
Deadly six-vehicle crash on Highway 400 sparked by road rage incident
One person was killed in a six-vehicle crash on Highway 400 in Innisfil Friday evening.
California Disney characters are unionizing decades after Florida peers. Hollywood plays a role
California performers are organizing to be represented by a union now, more than four decades after their Florida counterparts did so.
Opinion I just don't get Taylor Swift
It's one thing to say you like Taylor Swift and her music, but don't blame CNN's AJ Willingham's when she says she just 'doesn't get' the global phenomenon.
What is a 'halal mortgage'? Does it make housing more accessible?
The 2024 federal budget announced on April 16 included plans to introduce “halal mortgages” as a way to increase access to home ownership.