Regulator rules in favour of Trans Mountain route deviation

The Canada Energy Regulator has approved Trans Mountain Corp.'s application to modify the pipeline's route, a decision that could spare the government-owned pipeline project from an additional nine-month delay.
The regulator made the ruling Tuesday, just one week after hearing oral arguments from Trans Mountain and a B.C. First Nation that opposes the route change.
It didn't release the reasons for its decision Tuesday, saying those will be publicized in the coming weeks.
By siding with Trans Mountain Corp., the regulator is allowing the pipeline company to alter the route slightly for a 1.3-kilometre stretch of pipe in the Jacko Lake area near Kamloops, B.C., as well as the construction method for that section.
Trans Mountain Corp. had said it ran into engineering difficulties in the area related to the construction of a tunnel, and warned that sticking to the original route could result in up to a nine-month delay in the pipeline's completion, as well as an additional $86 million more in project costs.
Trans Mountain has been hoping to have the pipeline completed by early 2024.
But Trans Mountain's application was opposed by the Stk’emlúpsemc te Secwépemc Nation, whose traditional territory the pipeline crosses and who had only agreed to the originally proposed route.
In their regulatory filing, the First Nation stated the area has "profound spiritual and cultural significance'' to their people, and that they only consented to the pipeline's construction with the understanding that Trans Mountain would minimize surface disturbances by implementing specific trenchless construction methods.
The Stk’emlúpsemc te Secwépemc argued that Trans Mountain never said its originally proposed construction method was impossible, only that it couldn't be done in time to meet a Jan. 1 in-service date for the pipeline.
The First Nation didn't respond to a request for comment by publication time.
The Trans Mountain pipeline is Canada's only pipeline system transporting oil from Alberta to the West Coast. Its expansion, which is currently underway, will boost the pipeline's capacity to 890,000 barrels per day (bpd) from 300,000 bpd currently.
The pipeline — which was bought by the federal government for $4.5 billion in 2018 after previous owner Kinder Morgan Canada Inc. threatened to scrap the pipeline's planned expansion project in the face of environmentalist opposition and regulatory hurdles — has already been plagued by construction-related challenges and delays.
Its projected price tag has since spiralled: first to $12.6 billion, then to $21.4 billion and most recently to $30.9 billion (the most recent capital cost estimate, as of March of this year).
Keith Stewart with Greenpeace Canada said it's alarming to see the regulator over-rule the wishes of Indigenous people in order to complete a pipeline on deadline.
"Every Canadian should be outraged that our public regulator is allowing a publicly owned pipeline to break a promise to Indigenous people to protect lands of spiritual and cultural significance," Stewart said.
The federal government has already approved a total of $13 billion in loan guarantees to help Trans Mountain secure the financing to cover the cost overruns.
Trans Mountain Corp. has blamed its budget problems on a variety of factors, including inflation, COVID-19, labour and supply chain challenges, flooding in B.C. and unexpected major archeological discoveries along the route.
Given the Canadian regulatory system has a reputation for being slow and cumbersome, it was surprising to see the Canada Energy Regulator rule so quickly on Trans Mountain's route deviation request, said Richard Masson, executive fellow with the University of Calgary's School of Public Policy.
"It's a challenging decision to have to make, when you've got a $30 billion pipeline that needs to be completed," Masson said.
"If there's no feasible way to do that tunnel, then I guess you have to allow for this."
Masson added that if the regulator had denied Trans Mountain's request, it would have been bad news for taxpayers as well as the federal government, which is seeking to divest the pipeline and has already entered into negotiations with several interested Indigenous-led buyers.
It also would have been bad news for Canadian oil companies, who have been eagerly anticipating the pipeline's start date to begin shipping barrels to customers.
"If this can result in the pipeline being completed by year-end and started up in the first quarter, that's good news. The world is still looking for oil, and oil prices are up at US$90 a barrel," Masson said.
--
This report by The Canadian Press was first published on Sept. 25, 2023.
CTVNews.ca Top Stories

This Canadian couple used surrogacy to have a child. Here's what they want you to know
Families that need help conceiving a child are met with financial burdens that should be covered through government health care and insurance, advocates say.
Renowned Canadian musician and former April Wine singer Myles Goodwyn dead at 75
Myles Goodwyn, the award-winning Canadian singer and songwriter who shot to stardom as the former lead singer of April Wine, has died at age 75.
Renowned Quebec entrepreneur, partner reported dead in Caribbean
Quebec entrepreneur Daniel Langlois and his spouse Dominique Marchand have died in their adopted home of Dominica, in the Caribbean, a source has confirmed.
Another inmate dead at notoriously harsh Newfoundland jail, officials confirm
An inmate has died at Her Majesty's Penitentiary in Newfoundland, one of the oldest operating provincial jails in the country, officials with the provincial Justice Department confirmed.
Ships face Houthi-claimed attack in Red Sea as officials say a U.S. warship also fires in self-defence
Commercial ships came under attack Sunday by drones and missiles in the Red Sea and a U.S. warship there opened fire in self-defence as part of an hourslong assault claimed by Yemen's Houthi rebels, officials said.
Fatal stabbing of German tourist by suspected radical puts sharp focus on Paris Olympics
A bloodstain by a bridge over the Seine river was the only remaining sign on Sunday of a fatal knife attack 12 hours earlier on a German tourist, allegedly carried out by a young man under watch for suspected Islamic radicalization.
Venezuelans vote in referendum over large swath of territory under dispute with Guyana
Venezuelans are voting in a referendum Sunday called by the government of President Nicolas Maduro to claim sovereignty over a large swath of neighbouring Guyana, arguing the oil- and mineral-rich territory was stolen when the border was drawn more than a century ago.
Israel says military offensive in crowded southern Gaza will be 'no less strength' than in the north
The Israeli military said Sunday its ground offensive had expanded to every part of Gaza, and it ordered more evacuations in the crowded south while vowing that operations there against Hamas would be 'no less strength' than its shattering ones in the north.
Kyiv investigates allegations Russian forces shot surrendering Ukrainian soldiers
Ukrainian officials on Sunday launched an investigation into allegations that Russian forces killed surrendering Ukrainian soldiers -- a war crime if confirmed -- after grainy footage on social media appeared to show two uniformed men being shot at close range after emerging from a dugout.